Product Upgrade and Rollback

For sidecars and centralized gateways, clone a version-specific instance when scheduling an upgrade. Retain the previous instance, configuration, and pipeline for rollback and continued editing. Publishing a product release alone changes no deployments; upgrade fleets in batches.

This is an operator-controlled policy. The runtime contract records current limitations, including Java DCL snapshot consistency, provenance, and compatibility.

Emergency rollback checklist

Use the prequalified rollback mode. For a healthy old blue/green cohort, verify it and switch traffic without restarting it or changing its files. A remote-only rollback needing a restart depends on Config Server availability; see rollback availability.

  1. Record: retrieve the previous release record, artifact, snapshot/bundle, pipeline inputs, and migration recovery constraints.
  2. Reservation: take control of the existing release reservation with its owner; prevent competing deployments and configuration changes.
  3. Hold: block new traffic to unhealthy workloads and hold incompatible reloads/restarts. For a same-identity restart, stop the incompatible cohort before changing its snapshot. See rollback coordination.
  4. Directory, for this pipeline-controlled start: remote mode needs a pre-created writable directory without values.yml; local mode needs the recorded export. Preserve bootstrap material and exclude candidate files.
  5. Activate or install: activate the saved snapshot or install the qualified local bundle, then start the old artifact with its old pipeline.
  6. Startup checks: reject fallback and any download/write failure, verify the file inventory and runtime health, and keep the DCL logger at INFO.
  7. Traffic: admit traffic only to verified old-version workloads; for blue/green, switch to the healthy old pool.
  8. Evidence: record results and verification limits, obtain rollback approval, then end the freeze/reservation. Defer retirement until the group is stable.

Configuration loading modes

A Java DCL runtime loads its configuration at startup in one of two modes. The release record names the mode qualified for each release.

ModeHow configuration arrivesStartup dependency
Remote mode (normal)light-config-server-uri is set. DefaultConfigLoader calls Config Server /configs, /certs, and /files for host + serviceId + envTag, receives the current snapshot for that identity, and writes values.yml, certificates, and files into the config directory.Config Server must be available.
Local-export mode (contingency)light-config-server-uri is absent from every property/environment source. The pipeline installs a previously exported, approved bundle (values.yml, certificates, files) into the config directory, and the runtime starts from those local files.None on Config Server; the bundle must be retained and checksummed.

In remote mode, a pipeline-controlled start must use a writable directory with no values.yml. Otherwise a failed download can fall back to an existing file, possibly the candidate’s, and the start still looks successful. See startup checks.

Local-export mode is a rollback contingency, not a replacement for remote mode. Qualify it before the upgrade when a restart-based rollback must survive a Config Server outage; see rollback availability.

Configuration identity decision

Keep the Config Server lookup identity:

host + serviceId + envTag

Activate the approved snapshot for that identity; configPhase selects its phase. Keep product_version_id in the instance and its unique index to retain version-specific authoring state. Instance UI flags do not select the served snapshot or identify the running binary.

Qualify binary/configuration compatibility before activation: the Portal server ignores legacy productVersion parameters, and Java DCL has no active version guard. See the identity and compatibility decision.

Preserve the complete deployable release

Record the instance/product version, runtime identity, snapshot, deployment binding, pipeline, artifact, inputs, and verification evidence using the template below. Pin pipeline source/scripts/templates and binary/image checksums: pipeline IDs and moving image tags alone cannot reproduce a release. Preserve access to the required credentials through secret-manager references.

Retain both the editable instance and deployment recipe. Snapshot activation selects configuration; redeployment installs the old binary. Shared settings, external-state migrations, and editable graphs require their own recovery plan.

Release record location and template

The owning service/platform team designates a deployment configuration repository and publishes its URL/on-call owner in the service catalog or change register. Store records at release-records/<host-id>/<deployment-group>/<release-id>.yml, using a stable, path-safe group name. Link commit permalinks from the change ticket, pipeline run, and snapshot description. Retain input revisions and attempt history, accessible to on-call staff even when Portal is unavailable.

This template is an operational convention, not an automatic Portal export. Use one record per deployment binding, with fleet records linking members. Keep secrets and configuration bundles in restricted artifact storage.

releaseId: "gateway-2.3.9-attempt-1"
recordRepository: "<canonical team deployment configuration repository URL>"
recordOwner: "<owning service/platform team and on-call contact>"
deploymentGroup: "production-gateway"
runtimeIdentity:
  hostId: "<host UUID>"
  host: "<host name>"
  serviceId: "light-gateway"
  envTag: "prod"
instanceId: "<instance UUID>"
productVersionId: "<product-version UUID>"
productVersion: "2.3.9"
deploymentInstanceId: "<deployment binding UUID>"
artifact: "<immutable image digest or binary URI plus checksum>"
pipeline:
  id: "<pipeline UUID>"
  sourceRevision: "<immutable pipeline/scripts/templates revision>"
  inputsRef: "<restricted input artifact URI plus checksum>"
  credentialRef: "<secret-manager reference, never a credential>"
configuration:
  mode: "current-snapshot" # or qualified local-export deployment
  modeQualificationRef: "<successful pre-upgrade test of this release/mode>"
  rollbackAvailabilityRef: "<tested local-export contingency or approved Config Server dependency>"
  snapshotId: "<approved snapshot UUID>"
  configPhase: "R"
  responseDigest: null # capture the raw /configs response digest when served
  bundleRef: "<restricted values/certs/files artifact plus inventory/checksums>"
  authoringBaselineRef: "<reviewed graph revision/export/diff reference>"
rollbackRecord: "<previous release record commit permalink>"
coordination:
  reservationRef: "<exclusive pipeline lock/run or serialized change ticket>"
  changeFreeze: "clone through observation completion"
  observation: "24h production, including a representative traffic cycle"
  rollbackCriteriaRef: "<approved health, traffic and compatibility thresholds>"
  operator: "<deployment owner/on-call role>"
  approver: "<service/release owner>"
evidence:
  pipelineRun: null
  runtimeVersionRef: null
  fetchAndFileVerificationRef: null
  runtimeReportedSnapshotId: null # unavailable in unmodified Java DCL
  assurance: "pending; distinguish external evidence from runtime attestation"
  completionApprovalRef: null
  retirementApprovalRef: null

The response digest covers /configs YAML, not a complete certificate/file bundle. Keep separate export/file checksums; a non-current candidate’s exported output is not itself a /configs response. DCL reserializes values before writing values.yml, so its local file hash need not equal the response digest.

Retain at most two available instances

Apply one limit per logical deployment group: at most two available Portal instances and one upgrade in progress across all its versions, runtime identities, and replicas. Record the group’s member identities in the release plan. Normally a group has one (host_id, service_id, env_tag); blue/green adds two cohort identities to the same group, not two separate retention budgets. For sidecars, the group normally represents one API’s sidecar deployment and all its replicas, not each Pod and not the entire fleet. Keep:

  1. The currently deployed, verified instance.
  2. Either the previous working instance or the next upgrade candidate.

The words current release, rollback release, candidate, and retired describe operational roles in this guide; they are not new database status values.

A strict two-instance policy uses the following transitions:

StageAvailable instanceAvailable instanceRetired instance
2.3.8 is running and verified2.3.8 current2.3.7 rollbackOlder releases
Begin the 2.3.9 upgrade2.3.8 current2.3.9 candidate2.3.7
2.3.9 succeeds and passes the observation period2.3.9 current2.3.8 rollback2.3.7
2.3.9 fails2.3.8 currentOptionally restore 2.3.7Failed 2.3.9

Before creating 2.3.9, retire 2.3.7 only after 2.3.8 is verified stable and the operator accepts that 2.3.7 will require restoration if needed again. Do not retire an older release just because a higher version exists. If retaining immediate access to both existing releases during preparation is required, the policy must explicitly allow a temporary third candidate.

The limit bounds the normal UI working set, not database storage. Soft-deleted instances, events, snapshots, and deployment history still occupy storage and need a separate retention/recovery policy. Do not hard-delete old instances as routine cleanup: snapshot foreign keys include ON DELETE CASCADE.

Release controls

Record these operator-managed controls before starting:

  • Reserve the deployment group with an exclusive pipeline lock covering all cohorts and manual operations. Without a shared lock, designate a release manager to serialize runs in one change register. Record the owner/active run, investigate abandoned runs before takeover, and release the reservation only after completion or verified rollback. A ticket alone provides no lock.
  • Freeze API onboarding and configuration changes from the source baseline through observation completion. This has an onboarding cost for shared gateways. Blue/green shortens cutover downtime; ending the freeze early also requires an approved dual-update policy. For that policy or an emergency exception, apply equivalent supported changes to both retained instances, requalify snapshots/rollback records, and restart observation. Complete both records before declaring onboarding complete. If the rollback version cannot support equivalent behavior, maintain the freeze or pause the upgrade.
  • Use a default observation period of 24 hours in production, including a representative traffic cycle, and 30 minutes in staging. The service owner may approve a different period in the release record before rollout.
  • Define readiness deadlines and error-rate/latency thresholds and intervals. Roll back on missed deadlines, failed required route/authentication/authorization checks, incompatible configuration, or sustained threshold breaches. Require fetch/file evidence for promotion. Use the qualified migration recovery plan when external-state changes make binary rollback unsafe.
  • The deployment operator executes the change and may invoke the preapproved rollback criteria without waiting for another approval. The service/release owner approves completion and retirement after reviewing evidence. Record these approvals explicitly; passing a pipeline job is not approval.

Upgrade procedure

1. Qualify the target release

Register the target product version, its configuration/property mappings, configuration profiles, schemas/defaults, and supported deployment pipelines. Record property additions, removals, renamed keys, changed types/defaults, and any deployment or external-state migration requirements.

Check that the old pipeline and binary can still run. If the new release makes an irreversible external-state change, an old instance and snapshot alone are not sufficient recovery; qualify that release’s migration/recovery procedure.

Record and test the previous release’s rollback loading mode now. Local-export mode is eligible only after that old artifact, pipeline, bootstrap, and complete exported bundle have passed a deployment test together. Do not first switch to local-export mode during an emergency because Config Server is unavailable.

Rollback availability

If only remote mode was qualified and Config Server is unavailable, rollback requiring an old-binary restart is blocked. A healthy running blue/green cohort can still receive traffic; this protection ends if it also needs a restart. For critical centralized gateways, qualify a local-export contingency before the upgrade, or record Config Server availability as an explicitly accepted rollback dependency. Link the test or dependency approval in the release record.

2. Prepare the source and retention slot

Identify the deployed instance, rollback snapshot, and pipeline inputs. Compare its editable graph with the deployed snapshot: cloning copies the projected authoring graph. Resolve or explicitly include pending changes before cloning.

Acquire the release reservation and begin the change freeze. Reconcile any changes since the recorded baseline before cloning. Keep the freeze through observation unless the approved dual-update policy is in place, so the rollback instance does not lose newly onboarded APIs.

If two instances are already available, apply the retention rule before creating another. Never retire the current release or a release with running workloads, an unfinished deployment, or a required immediate rollback role.

3. Clone the version-specific candidate

Use Instance Admin → Clone and the Clone an Instance workflow. For a same-identity rollout, retain the production service ID and environment tag; for a separate-cohort rollout, select the approved cohort identity. Explicitly select the target product version. Select Environment independently from Env Tag; they are different inputs.

Review APIs, apps, properties, and optional files/deployments (excluded by default). Verify credentials separately: OAuth clients/tokens, deployment runs, and runtime instances are outside clone scope. A same-identity clone may reuse valid Config Server authorization; separate cohort identities need credentials authorized for their host/service/env context.

Leave “Create current snapshot” unchecked (createSnapshot=false). Enabling it would replace the served snapshot for a shared identity before review/deploy.

Plan and execute once, then wait for PROJECTED. Reuse the original request identity when checking a timed-out request. Treat FAILED_DLQ as a recovery case; do not blindly submit a fresh clone request.

4. Review configuration and select the target pipeline

Validate the candidate against the target release:

ChangeRequired review
New optional propertyConfirm its target default and whether an override is needed.
New required propertySupply a valid value if no usable default exists.
Changed defaultCompare effective values and retained explicit overrides.
Renamed property or changed type/meaningApply the release migration and validate the resulting value.
Deprecated propertyRetain it only while supported by the target release.
Removed propertyOmit it from the candidate output while preserving the older instance/history.

Preserve catalog properties used by older releases. Review mappings, profiles, approved extensions, inherited overrides, and required defaults in the actual generated output. Editor visibility alone cannot establish release support. If excluding an unsupported inherited value would affect other instances’ shared settings, stop and resolve the generation gap. See applicability/defaults follow-ups.

Explicitly bind every candidate deployment to a pipeline supported by the target version/environment; cloned deployments retain their original pipeline IDs.

5. Create and verify a candidate snapshot

After configuration/deployment projections catch up, create a snapshot with current=false and pass the graph-readiness/revision check.

Iterating on the candidate does not create instances. Edit the same cloned candidate and create another non-current snapshot for each review or test round: twelve configuration fixes produce one candidate instance and twelve snapshots. Delete unneeded candidate snapshots with the snapshot delete command, but keep every snapshot that was deployed, approved, or referenced by a release record, and keep the rollback snapshot.

Use snapshot output and comparison to review the candidate against the retained rollback snapshot. Check both values and their sources, required configuration, selected files/certificates, API routes, and the deployment inputs. Record the candidate snapshot ID and checksums of the approved exports. Freeze its release inputs or repeat validation if they change.

Check actual snapshot output where environment and product-version values compete; editor precedence currently differs. Preserve referenced catalog names and metadata through retention to keep output reproducible. See the implementation limits.

6. Deploy, activate, and observe

Test the target artifact using the approved exported configuration, or use an isolated test deployment with its own authorized identity. Do not activate a candidate on the production identity merely to download it for a test.

/configs always selects current, ignoring snapshotId. Ancillary endpoint pinning alone does not enable a pinned deployment. See the snapshot-selection contract.

Choose a rollout procedure that respects this limitation:

  • If old and new binaries can consume the same configuration during overlap, validate that compatibility and coordinate activation with deployment.
  • If they require different configurations, use a maintenance window that drains/stops the old release before activation/startup, or use the separate-cohort procedure. Hold automatic restarts and all manual/controller-triggered configuration reloads on old processes during the transition. Snapshot activation affects subsequent reloads as well as new starts; it is not itself a reload broadcast. Transparent per-deployment snapshot selection under one identity requires code changes.

Run the selected target pipeline with the approved artifact and inputs. Activate the candidate snapshot at the point required by the chosen rollout procedure, then follow the DCL startup checks. Verify the running product version, readiness, and representative API traffic. A submitted job, successful clone, or UI flag alone does not establish success.

Keep the previous instance available throughout the observation period. Mark the release transition complete only after runtime verification. Do not start the next upgrade for the deployment group while this transition is unresolved.

Java DCL startup and configuration evidence

These gates apply to rollout/rollback starts and retries controlled by the release pipeline. The pipeline enforces the no-cache preparation and rejects fallback for those attempts; do not install a permanent init step that deletes values.yml on every boot. After release verification, steady-state liveness restarts, evictions, and scale-out follow the normal runtime fallback policy. Retain release-scoped storage; changing that ongoing policy belongs to F7. Custom loaders and Rust runtimes need their own qualified procedure.

Keep com.networknt.server.DefaultConfigLoader at INFO or more restrictive, even when parent loggers use DEBUG. Use INFO for source verification; DEBUG/TRACE can expose values and base64 certificates/files. Restrict access to error logs, which can contain response bodies. See the implementation table for the code paths behind these gates.

  1. Prepare the controlled start. In remote mode, pre-create a writable release directory with approved bootstrap templates/trust material and no values.yml. For prequalified local-export mode, install the recorded complete bundle, including values, and disable remote loading. Qualify any bootstrap that requires seeded values before adopting the remote-mode gate. When reusing a volume, stop the process, archive it securely, and reconcile loader-owned files against the approved inventory. Preserve independent credentials/bootstrap files. Repeat preparation for a pipeline retry after partial startup; exclude the candidate’s values/files from an old release.
  2. Hold activation and reloads. Keep the selected snapshot fixed across /configs, /certs, /files, and retries. Use a controlled restart for cert/file changes; DCL reload refreshes values only.
  3. Reject failed remote starts. Require Server startup config source: config server, successful downloads, and successful writes. Any fallback/source-cache message, empty/unusable values, or download/write error fails the release attempt: stop/quarantine it and admit no traffic. The shared Failed to load configs from config server with status message also covers cert/file calls. A values-source success message alone is insufficient; verify all three downloads and the resulting inventory.
  4. Verify and record. Check the running version, health, representative traffic, effective values, and complete file inventory. While activation is held, compare an authorized server fetch with local YAML semantically and verify file checksums. Correlate deployment/server-side request evidence where available. Java DCL provides no runtime-reported snapshot ID/digest: leave that manifest field unset and label the evidence external. If runtime attestation is required, hold the rollout pending instrumentation. See evidence limits.

Centralized gateway blue/green example

Config Server selects configuration only by host + serviceId + envTag, and /configs always serves that identity’s current snapshot. Two deployments that share an identity therefore always receive the same configuration:

  • Compatible releases: if old and new binaries can consume the same configuration, separate identities are unnecessary. A rolling update or an existing blue/green traffic switch under one identity works as is.
  • Incompatible releases: if the new release needs different configuration, activating its snapshot on a shared identity also changes what the old cohort receives on its next restart, eviction, or reload, so the rollback target no longer has its old configuration. Give each cohort its own identity.

For incompatible releases, use two runtime identities behind one stable public gateway address. Both use the same tenant host and serviceId=light-gateway; blue uses envTag=prod-blue, green uses envTag=prod-green. The cohorts alternate:

StageBlue (prod-blue)Green (prod-green)Public traffic before canary
Prepare 2.3.92.3.8 current2.3.9 candidateBlue 100%
2.3.9 passes observation2.3.8 rollback2.3.9 currentGreen 100%
Prepare 2.3.102.3.10 candidate; 2.3.8 retired first2.3.9 currentGreen 100%

The strict two-instance limit leaves 2.3.9 without a warm rollback during 2.3.10 preparation. Recovering retired 2.3.8 can require rebuilding its pools, routing, and credentials as well as restoring Portal state. Accept that recovery time explicitly, or approve a temporary third instance and retain its warm infrastructure through preparation.

Both instances can select the production Environment; Env Tag is the separate snapshot/authorization identity, not that environment selector.

  1. Preserve the blue instance, approved snapshot, pipeline, and deployment. Clone green with the target product version and prod-green, with automatic current-snapshot creation disabled. Use the shared reservation and deployment-group retention rule.
  2. Bind green’s pipeline/bootstrap to prod-green and credentials authorized for that host/service/env context. Review env-tag-dependent discovery, controller registration, routing, and policies. Provision separate upstream pools so the traffic switch can distinguish blue and green replicas.
  3. Approve and activate green’s snapshot only on prod-green; leave blue’s current snapshot unchanged. Start green using its own config volume and run the startup checks. Route test/canary traffic through the load balancer, then increase its share against the recorded health/traffic criteria. Snapshot activation is not the traffic switch.
  4. During observation keep blue ready with its own pipeline/configuration. Roll back by directing traffic to healthy blue replicas, redeploying blue with the saved inputs if needed. Never point a blue binary at prod-green.
  5. After completion keep blue as the retained rollback release. At a later authorized retirement, remove it from routing/discovery, drain/stop its workloads, disable redeploy/reload triggers, and clear its current snapshot selection before soft retirement. Retire unused cohort credentials only when no retained recovery procedure or other deployment needs them. Do not rename the surviving instance’s identity to collapse the cohorts.
  6. For 2.3.10, obtain retirement approval for blue 2.3.8 and complete step 5’s cleanup first. Clone the verified green 2.3.9 authoring instance into a new 2.3.10 instance targeting prod-blue, with createSnapshot=false. This is an explicit cross-env-tag clone; keep the intended production Environment and review copied environment-dependent values, files, authorization, and pipeline bindings. Do not switch the old 2.3.8 instance’s version. Its retired row remains in history alongside the new active 2.3.10 row in prod-blue, but only green 2.3.9 and blue 2.3.10 count as available. Activate blue’s approved new snapshot and repeat the checks/canary; green remains the rollback target. If that exact target version already exists retired, restore/reconcile it using the retry procedure instead of creating another row.

Kubernetes Service-selector variant

On Kubernetes, perform blue/green at the Service level, the same way it is done for other workloads. The “load balancer” and “upstream pools” above map to:

  • Two Deployments, for example light-gateway-blue and light-gateway-green, each labeled with its color (color: blue / color: green).
  • One stable Service whose selector chooses the live color. The cutover, canary completion, and rollback are all a change to that selector.

For incompatible releases, the only Portal-specific addition is that each Deployment carries its own configuration identity: set envTag to prod-blue or prod-green in that Deployment’s bootstrap/environment, bind it to its own Portal instance and snapshot, and give it credentials authorized for that env tag, as well as its own config volume. If both Deployments share one env tag, a selector switch still moves traffic correctly, but snapshot activation changes what the old color loads on any Pod restart or reload. For compatible releases, Service-level blue/green with a single env tag needs none of this.

A weighted canary needs a mechanism beyond a plain selector switch, such as a gateway or service-mesh traffic split, or a temporary Service selecting both colors by a shared label.

Different serviceId values can also separate cohorts, but require equivalent authorization, discovery, and routing review. Reusing a cohort/version already in history follows the retry/restoration procedure below.

Rollback procedure

  1. Select the retained previous instance, approved snapshot, binary/image, and pipeline revision from the release record.

  2. Coordinate traffic and process shutdown/startup so each binary receives compatible configuration. Retain the release reservation; hold incompatible processes’ reloads and automatic restarts. Prepare the previous release’s configuration directory using the DCL checks above.

  3. Use the loading mode recorded and qualified for the previous release:

    • Current-snapshot mode: activate the saved previous snapshot for the old runtime identity, then redeploy the old artifact using its saved pipeline and inputs. Keep activation fixed until all startup downloads finish. With separate cohorts, blue may already have the correct snapshot; verify it and switch traffic only after confirming blue is healthy.
    • Local-export mode: have the pipeline install the previously approved values, certs, and files using the old release’s tested local-only bootstrap. Ensure light-config-server-uri is absent from every property/environment source. Use this mode only when its pre-upgrade qualification is recorded; otherwise follow the availability dependency.

    Consume the saved snapshot/export. Regenerating from current authoring tables creates different inputs, and /configs?snapshotId=... is ignored today.

  4. Complete the DCL fetch/file checks for remote mode, or verify installed bundle checksums for local mode. Record the actual runtime version, readiness, API traffic, and the configuration evidence/limitations. Do not claim that unmodified Java DCL reported a snapshot ID or digest.

  5. Retain the failed candidate for diagnosis or soft-retire it when safe. If the two-instance policy requires restoring an older release, retire the failed candidate first and use the supported lifecycle restoration procedure. Obtain approval of the verified rollback outcome, end the change freeze, and release the reservation only after the deployment group is stable.

Redeploy the retained old instance rather than changing the candidate’s version. Resume onboarding there after rollback; create new snapshots for new edits and preserve the original rollback snapshot. Reconcile APIs added only to the newer instance and review shared catalog/inheritance changes.

Retry a failed product-version upgrade

This section covers a release attempt that was declared failed, rolled back, and retired. Fixing configuration during an unfinished attempt is not a retry: edit the same candidate and create another snapshot, as described in step 5. Each retry reuses the same instance row, so repeated attempts add snapshots and release records, not instances.

After a failed 2.3.9 upgrade is retired, its row still reserves (host_id, service_id, env_tag, product_version_id). Clone checks include retired rows. A fresh clone of 2.3.8 into that same 2.3.9 identity will be rejected, even with a new instance UUID.

  1. First finish or repair the original clone/deployment attempt, including any FAILED_DLQ projection, and establish a stable running release. A command retry and a new release attempt are different operations.
  2. Acquire the same release reservation and apply the two-instance retention rule. For example, retire a restored 2.3.7 rollback instance before restoring 2.3.9, keeping verified 2.3.8 available throughout.
  3. Restore the existing 2.3.9 instance and required cascaded children through the lifecycle workflow. Confirm projection completion and inspect the restored graph, files, and deployment bindings; restoration is not a re-clone.
  4. Reconcile the restored candidate with the latest approved 2.3.8 baseline, including APIs onboarded since the first attempt. Review a three-way diff where possible: original source baseline, current source, and failed candidate. Use normal editing commands to apply the selected changes and the 2.3.9 migration again. Clone does not provide a merge-into-existing-target operation. If the original baseline is unavailable, perform a full comparison and configuration review before proceeding.
  5. Create a new non-current snapshot and a new attempt-specific release record referencing the same candidate instance ID. Preserve the first attempt’s snapshot/evidence. Repeat validation, deployment, and observation; do not reuse approval from the failed attempt.

Do not hard-delete the retired row or silently replace it with a new clone to bypass uniqueness. Portal is event-sourced: a direct database delete bypasses the event store, leaving projections and events inconsistent, and snapshot foreign keys cascade the delete to that attempt’s snapshots. Clean up with lifecycle commands instead: soft retirement/restoration for instances and the snapshot delete command for unneeded candidate snapshots.

Safe retirement and recovery

Use Portal lifecycle commands/events for soft retirement; owned graph rows are cascaded, snapshots/history retained, and the instance hidden from normal lists. First clear selected current snapshots and confirm there are no running deployments or required rollback obligations. Operators enforce these gates; soft retirement alone leaves selected snapshots servable. See the implementation table.

Preserve shared product versions, pipelines, artifacts, and access needed by other instances or the recovery plan. Qualify restoration of the instance, cascaded children, and deployment infrastructure before relying on archives. Retired rows still reserve their version identity: use the restore/retry procedure.

Fleet operation

Sidecar version overlap

A Kubernetes Deployment normally uses RollingUpdate, so old and new Pods can overlap under the same Config Server identity. Recreate stops the old revision before creating the new revision during a Deployment upgrade; it does not give the same guarantee for manual Pod deletions or other controllers. See the Kubernetes Deployment strategy contract.

Choose and record one policy for each API’s sidecar deployment group:

  • Compatible rolling update: qualify the served values, certs, and files for both old and new binaries, including old-Pod restarts/reloads and rollback while any new Pods remain. Use that approved common configuration throughout the overlap; do not rely on old Pods retaining a cache. Keep activation fixed through each complete DCL download sequence.
  • Incompatible versions: use a qualified Recreate rollout or a maintenance restart, accepting the API/application Pod outage. The pipeline must ensure old consumers are stopped, activate the target snapshot, then permit new startup. Recreate alone does not schedule the external snapshot activation: use a tested startup gate or an explicit scale-down/wait/activate/start sequence. Hold autoscaler/GitOps reconciliation and other deployment/reload triggers during that sequence. Coordinate every workload sharing the identity, not just one Deployment, and use the same ordering for rollback.

If neither policy is acceptable, stop and design isolated identities or a qualified pinned/local-export deployment before rolling out. Per-Pod blue/green env tags are not the default fleet strategy. Batch by independent deployment groups; batching does not solve incompatible overlap within a group.

Batch coordination

For sidecar fleets, automate the reviewed workflow around existing commands: select eligible instances, reserve one upgrade per deployment group, clone in bounded batches, validate, deploy in cohorts, and record each result. Preserve the request identity across retries and distinguish accepted commands from fully projected and runtime-verified outcomes.

Apply the shared deployment-group retention rule after its own transition checks; a successful fleet subset must not cause retirement for a failed or unfinished instance. The current UI is not a fleet upgrade orchestrator, and a batch implementation is additional work.

Related reading: Instance Clone design, Configuration Snapshots, Config Server operations, and Policy-Driven Cascade Delete. For source evidence and proposed code work, see Product Upgrade Runtime Contract.